Model Guideline #13 - Part B

Show me typical guidelines for -

Project Cost Estimating: Planning Phases

Particulars - 1

Project Cost Estimating in the Planning Phases provides the basis for

Particulars - 2

Note: Cost estimating & control in the planning phases takes place on two levels

Particulars - 3

The Order of Magnitude Estimate is really no more than an "educated guess" based on

Note from the accuracy ranges suggested that

Particulars - 4

The Definition Class Estimate is

And is based on

Particulars - 5

In addition, the Definition Class Estimate must allow for

This, and following estimating, should be

Particulars - 6

The Implementation Class Estimate is

And is based on

Particulars - 7

For purposes of the Project Charter

The reason for this "conversion" is because the way costs are estimated is not the same way as they are usually collected

Particulars - 8

To enable project cost monitoring and control

Special vigilance is required in this conversion process

Particulars - 9

A cost estimate may, or may not, include an assessment of appropriate contingency allowance However,

Estimates at all stages must include all applicable charges such as

Definitions and Responsibility

Definitions to be included

Primary responsibility

Responsible to