

Contract Formulation - Part B
What are the considerations in preparing and forming a contract? Especially quality and work control, pace and compensation
Contract Formulation
Continued from Issacon #1412 - Part A
Caveat
Note: We are not lawyers, we cannot provide legal advice
· Legal texts should be reviewed by legal experts
· Knowledgeable in the law of the relevant jurisdiction
Control of the work - 1
·
The acquirer's control-of-the-work
variable
· Is the extent to which the acquirer wishes to exercise control
· Over the work to produce the product
·
For example
· Control over a "time-and-materials" contract is complete
· Control over a fixed-price contract is minimal
· If the acquirer wishes to avoid any supplier claims for "interference"
Control of work - 2
·
The supplier's control-of-the-work
variable
· Is really the converse of the acquirer's control
· And is the extent to which the supplier has control
· And hence responsibility
· For the performance of the product
·
For example
· The supplier's control, and interest in control, is minimal
· In the case of a "cost-plus" or "time and material" form of contract
Quality control
·
The quality control variable
· Is the extent to which the acquirer takes responsibility for quality assurance, control and testing
·
For example
· Quality control rests almost entirely with the supplier
· In a fixed price contract
· Although inspection and testing may be a condition of interim progress payments
Pace of work
·
The "pace of work" variable
· Depends on whether the rate of production is optimized
·
For example
· If the target delivery date is set sooner
· Than an optimal program of work suggests
· Then the work must be accelerated
· By applying additional resources, or overtime
· Either may imply additional cost to perform
· And possibly additional risk due to increased complexity in coordination
· If the work is prolonged
· Extra costs result from idle capacity
Form of compensation - 1
·
The form of compensation
· Is not so much a variable
· As it should be a reflection of the other variables
· However, it does have a range of possibilities
·
Example 1
· If the scope requirements, or scope of work, are well defined
· A fixed price is in the best interests of the acquirer
· And the best opportunity for efficient operation and for profit by the supplier
Form of compensation - 2
·
Example 2
· If the conditions suited to a fixed price form of contract are not met
· A fixed price contract may well end up being more costly to "retro-fix"
· Or even end up in failure
·
Example 3
· The software industry is rife with failed projects
· Due to the application of inappropriate forms of contract
· Not corresponding to the degree of scope definition
· To the detriment of both acquirer and supplier
Form of compensation - 3
·
Example 4
· A modified form of fixed price contract is possible
· Where provision is made for limited scope variations
· By incorporating one or more unallocated sums
· For use at the discretion of the acquirer
· Such a contract may or may not include incentives
·
Example 5
· Time and materials compensation is most appropriate
· Where the extent of the requirements are not yet known
· Or are highly uncertain
Supplier motivation - 1
·
The supplier's motivation variable
· Is the extent to which a supplier is motivated to perform efficiently
·
Example 1
· Motivation is high in any "fixed-price" or "lump-sum" contract
· It offers the opportunity to increase profit
· By performing most efficiently
· Providing that quality is not compromised
Supplier motivation - 2
Example 2
· Supplier motivation is probably highest
· In the supply of standard off-the-shelf products
· Since this provides the safest and quickest return to the supplier
· Standard products may or may not meet the acquirer's needs
· And may still require some degree of customizing
· But this solution is usually less risky to both parties
· Compared to an all-custom developed solution