C/P Administration & Closure - Part B
What else should I know about the C/P administration and closure processes?
Contract/Procurement Administration
Continued from Issacon #1405 - Part A
Contract claims
·
Reserve the term "claims" for work
that the supplier
· Considers is over and above the terms of the contract
· I.e. alleged additional work
· Don't use the word to refer to the supplier's normal invoices
· This just leads to confusion
·
Upon receipt of a claim
· Or even a notification of a potential claim
· Research, negotiate and settle or reject the claim
Handling claims
Many organizations
· Simply reject all claims automatically, out of hand
· This is a mistake
· Unless the claim is clearly spurious
· It is usually cheaper to settle at the time
· Than incur rancor and extensive legal bills
· And impede the progress of the work
Settling claims
·
The best way to settle a claim
· That has any degree of validity
· Is to negotiate a settlement
· And issue a change order accordingly
·
Needless to say
· Maintain a careful record
· Of all contract changes
Final acceptance and closure process
When all the work is supposedly complete
· Verify that the product meets all contractual requirements
· E.g. functionality, documentation, support, etc
· Ensure that all deficiencies have been corrected satisfactorily
· Or otherwise some adjustment is made to the contract price
· (Remember the law of diminishing returns!)
Product transfer
Once completion has been established
· Obtained corporate owner and/or users "sign-off" on the product
· Against a final acceptance checklist document
· And make arrangements for the transfer of the product
· And its care, custody and control
· Into the hands of the users
Contract closure
Final payment and audit
· Receive supplier's request for final payment
· And verify that it meets all the terms of the contract
· Obtain approval
· And pass the invoice to the accounting department for payment
· Arrange for a contract procurement audit, if required
· Close all associated accounts
· And archive all contract records
Final word
A final word to the supplier
· The real success of many projects, and contracts
· Comes down to a matter of perception
· It is worth spending a little energy
· On promoting the product to the users
· And helping them to get the most out of the product
· In which case, the users are much more likely to be forgiving
· Of a few minor initial operational glitches
· Even though these are quickly corrected