

How to Recognize Project Risks
How do I know if my project is at risk and, if so, what can I do about it?
Simple Indications
Some simple indications that a project is at risk:
· The project's sponsor does not recognized that every project is an exercise in risk
· No risks have been identified, or no appropriate contingency plans have been developed
· The project relies entirely on the contingency allowances
· The project's goals, objectives, scope and deliverables are not clearly defined, nor understood
· Costs, schedules and performance are not expressed in ranges
More simple indicators
· Future timing of activities and events are vague
· Standards for performance are absent or unrealistic
· "We expect the best there is for everything!"
· The project is very different from the last one
· A large number of alternatives are perceived as possible
· Some or all technical data is lacking
· Design lacks production or engineering input
· Prototype of a key element is missing
· There is a higher than usual R&D component
Still more indicators
· Some or all environmental considerations or permits are not considered or available
· Bids in response to requests for quotation vary widely
· Some key subsystems and/or materials are sole sourced
· There is a feeling of uneasiness
· Someone starts "hedging their bets"!
· Other similar projects have been delayed or canceled
What can I do about such a risky project?
·
Here are some simple rules-of-thumb
·
Don't continue the project, or accept one
of its risks, if:
· The organization cannot afford to lose
· The exposure to the outcome is too great
· The project, or situation, is just not worth it
· The odds are not in the project's favor
More simple rules-of-thumb
Discontinue the project, or avoid the risk if:
· It is seen as no more than a "fair bet"
· The benefits have not been identified
· There appear to be a large number of acceptable alternatives
· The greater the number, the greater the uncertainty
· One or more of the project's risks does not support the project objectives
Still more rules-of-thumb
Discontinue the project, or avoid the risk if:
· The Expected Value from the baseline assumptions is negative
· Or becomes negative with small changes in the assumptions
· The data is unorganized, without structure or pattern
· Get more data, or do research!
· A contingency plan is not in place should the results prove to be less than satisfactory
Bottom Line
A viable project is one in which the probability of gain is higher than the probable consequences of loss
1004 Project Risk
Key Words:
Project risk management, project risk, risk, uncertainty, opportunity
Area of PM Application: Universal
(See IAC #1001)
Topic Level: Process
(See IAC #1002)
Related Topics:
Reference:
What is project risk?
Be careful how you say it!
·
In project work
· Always refer to project risk
·
Why?
· Because use of the term "risk" (i.e. on its own) typically refers to risk as defined in the insurance industry
· Which commonly refers to something happening to you that you don't like!
·
Project risk is a special case of risk
· The risk of the project not being successful
· We'll deal with the insurance sort in a later Issacon
Dual meaning
·
In the literature, risk is often used to
imply simply failing to fall into line with the project plan
· Either over or under
·
This is really normal project progress
evolution
· And management's responsibility to track and control
· After all, schedules and budgets are only based on best estimates
· To be handled by management strategy, tactics and contingencies
Risk in Progress Evolution
·
If your project is viewed as unsuccessful
simply because
· It fell behind schedule
· Or went over budget
· Perhaps due to poor estimating
· Or to lower than planned productivity
·
Such situations are evolutionary - not
events
· That's not usually part of formal project risk management
· That's the project team's management responsibility
Event Oriented Project Risk
·
While risk is the possibility of an
undesirable outcome
· Formal Project Risk Management usually focuses on "Risk Events"
·
Thus
· Project Risk is the cumulative effect of the chances of adverse events which could affect the projectís objectives
· Or, the degree of exposure to untoward or turbulent events and their probable consequences
Appropriate Risk Event Response
·
Note the use of the word "events"
·
For identifying, analyzing and mitigating
unplanned events
· Or better still, avoiding them altogether
· Adopt some degree of formal project risk management
· And be ready with an appropriate response
Evolution versus Events
·
As your project evolves
· It may well fall behind schedule
· And run over budget
· Requiring corrective action
·
If, however, the corrective action fails
and you miss a mandated deadline as a result
· That is indeed an "event"
· For which you would be well advised to have a good risk management plan!